Work Breakdown Structure (WBS) in Scientific Research: A Practical Guide

A practical guide to breaking scientific projects into manageable work packages, with a numbered WBS example, dictionary template and EU funding context.

KaiperKit Team
27 min read

A scientific project may have a promising hypothesis, an approved budget and a skilled team, yet still prove difficult to coordinate. An experimental protocol depends on samples that have not arrived; data analysis requires measurements from another laboratory; a doctoral researcher shares equipment with several projects; and the funder's reporting deadline falls before validation is complete. The problem is not always a lack of planning. Often, the project's work has not been broken down into sufficiently clear components.

A Work Breakdown Structure (WBS) for a research project organises the full project scope into progressively smaller deliverables and manageable components. Its purpose is not to turn scientific discovery into a rigid checklist. Instead, it makes committed outputs, responsibilities, dependencies and scope boundaries visible to everyone involved.

This guide explains how to create a WBS for scientific research, how to adapt it to academic and R&D projects, how to define verifiable research work packages, and how it relates to the work packages used in European grant proposals. It includes a fully numbered WBS example, a reusable work package dictionary entry, an illustrative budget allocation and a planning checklist for principal investigators (PIs), project coordinators and research teams.

01 / DEFINITION

What is a Work Breakdown Structure (WBS) in scientific research?

A Work Breakdown Structure (WBS) is a hierarchical decomposition of a project's total scope. It begins with the overall project outcome and divides it into smaller components until the team reaches units of work that can be defined, estimated, assigned and monitored. The Spanish term Estructura de Desglose del Trabajo (EDT) refers to the same concept.

The Project Management Institute (PMI) presents the WBS as a deliverable-oriented representation of what a project needs to produce, rather than a schedule or a sequence of activities. ISO 21511:2018 provides guidance on work breakdown structures for project and programme management across sectors. Neither reference confines WBS to engineering or construction: the approach can be adapted to scientific work.

The essential WBS question

Rather than starting with “What should we do on Monday?”, start with “Which outputs and components must be delivered for the agreed project scope to be complete?” Activities, owners and dates can then be planned around those components.

Why is a WBS useful to a principal investigator?

A PI often coordinates funding, researchers, external partners, protocols, publications and reporting obligations. A WBS gives the team a shared language for explaining what is included, what remains outstanding, where effort is concentrated and what evidence will demonstrate completion. It does not replace scientific peer review or determine whether a hypothesis is correct.

For example, “research sustainable materials” is too broad to manage as a project component. A WBS might distinguish a “formulation protocol”, a “characterisation test dataset”, a “pilot prototype” and a “validation report”. Each can be decomposed into further verifiable outputs when necessary.

02 / STRUCTURE

WBS levels: projects, deliverables and research work packages

A WBS is usually displayed as a hierarchical tree or a numbered outline. The complete project sits at the top, with its major components beneath it and, at the agreed level of detail, research work packages that can be estimated and controlled. There is no universal number of WBS levels that suits every scientific project.

Illustrative breakdown of an R&D project's scope
Example levelWhat it representsExample
1.0Entire projectDevelopment of a packaging biomaterial
1.2Major component or outcomeExperimental formulation system
1.2.1Detailed element or manageable packageDocumented catalogue of candidate formulations
Related activityAn action needed to produce the element; usually scheduled outside the WBS treePrepare batches, measure viscosity, record parameters

Important: giving an element the code 1.2.1 does not automatically make it a work package. It becomes one when it is the lowest approved level at which its scope is managed. Another project might designate 1.2 as its lowest-level work package. The required depth depends on complexity, uncertainty, estimation and reporting needs.

The 100% rule: include the entire scope without duplication

A classic WBS principle associated with PMI is the 100% rule: the structure should represent all the work required to deliver the approved scope, and a parent element should be fully accounted for by its child elements. It should include internal outputs and essential management work while excluding activities that belong to other projects or scopes.

“100%” does not require every box to receive a percentage of the budget or staff hours. It is a principle of scope coverage and avoiding overlap. Resource and cost estimation comes afterwards, even though those estimates are organised around the defined work packages.

If a project requires ethics approval, data management, consortium coordination or evidence for grant reporting, those components should not disappear merely because they do not produce a research paper. Conversely, an unrelated investigation should not be added without reviewing the agreed scope and any necessary approvals.

Break work down by outputs, not merely by verbs

A WBS built entirely from actions soon becomes a task list. Deliverable-oriented descriptions are clearer: “cleaned dataset”, “validated protocol”, “documented analytical model”, “working prototype” or “results report”. Activities such as “review literature” and “conduct interviews” can subsequently be planned under the package that produces, for example, an evidence review or a documented dataset.

03 / KEY DISTINCTIONS

WBS vs Gantt charts, tasks, milestones and deliverables

The work breakdown structure in R&D establishes what needs to be delivered. It should not be confused with the planning and monitoring tools used later. Making this distinction helps teams avoid assuming that their research scope is adequately defined simply because activities have been placed on a calendar.

Complementary tools for planning scientific projects
Tool or conceptQuestion answeredExample
WBSWhich components make up the entire scope?Stability-test dataset
Work packageWhich scope unit can be estimated and controlled?Documented mechanical characterisation
Task / activityWhich action must be performed?Conduct tensile tests on samples
DeliverableWhat verifiable output is produced or submitted?Characterisation report with methods and data
MilestoneWhat control point has been reached?Protocol approved before validation
Gantt chart / scheduleWhen will activities happen and what depends on what?Testing during months 7–10, after the pilot batch
KanbanWhat is the current operational status?To do, in progress, under review, complete

A deliverable may belong to a package; a milestone can confirm that a condition has been met; and several tasks may contribute to one output. The Gantt chart adds timing, durations and dependencies, while Kanban supports day-to-day task monitoring. Neither tool alone defines the complete project scope.

For the wider lifecycle and planning methods, see our guide to R&D and innovation project management.

04 / SCIENTIFIC CONTEXT

How to adapt a WBS to uncertainty in scientific research

Researchers cannot always know in advance what an experiment will reveal. An initial design may show that a technique is unsuitable, that data are missing or that a hypothesis needs to be revised. This does not make a WBS inappropriate, but it does require a distinction between verifiable deliverables and positive scientific findings that cannot be guaranteed.

Define outputs you can verify without promising discoveries

“Prove that our material outperforms all competitors” may describe an ambition contingent on uncertain findings. As a manageable output, “comparative material-property report including the protocol, measurements and limitations” is more robust. The team can demonstrate that rigorous research was conducted even if the results do not support the initial hypothesis.

Similarly, an accepted journal article or awarded doctoral degree should not automatically be promised as a guaranteed project output when it depends on external editors, reviewers or examination boards. Where appropriate and agreed, controllable outputs may include a manuscript ready for submission, a curated dataset, a technical report or a thesis draft prepared for internal review.

Progressive elaboration, reviews and decision points

Exploratory projects may initially define near-term outputs in detail and leave later components at a higher level until uncertainty has been reduced. Progressive elaboration does not remove the 100% rule for the current approved scope: it identifies the work to be covered and refines the detail as sufficient evidence becomes available.

  • Hypotheses and alternatives: document possible experimental paths and the conditions that would trigger an alternative approach.
  • Acceptance criteria: define a verifiable output without equating it with confirmation of the hypothesis.
  • Decision gates: identify when to continue, adjust a method, repeat a measurement or request a scope change.
  • Change control: record amendments affecting deliverables, budgets, agreements or funding commitments.
  • Negative findings: retain rigorous data and conclusions even when the expected positive result is not obtained.

The purpose is to plan scientifically reasonable work, not to eliminate the uncertainty inherent in R&D.

05 / PRACTICAL METHOD

How to create a WBS for a research project in 7 steps

The WBS should be developed with the PI and the people who understand the protocols, equipment, datasets and scientific constraints. A structure drafted only by administrative staff may look comprehensive while leaving out essential laboratory or validation work.

  1. 01

    Define the objectives, scope and exclusions

    Agree

    Start with the project proposal, grant agreement, collaboration contracts and scientific requirements. State what must be delivered, what is outside scope and which ethical or regulatory requirements apply.

  2. 02

    Identify major deliverables and components

    Structure

    Consider methodological design, sample acquisition, experimentation, analysis, validation, data management and any committed dissemination outputs. These are examples rather than mandatory categories.

  3. 03

    Decompose them into manageable units

    Refine

    Break each component down until it has an identifiable owner, estimable effort and an objective completion condition. Avoid so much detail that maintaining the structure costs more than it helps.

  4. 04

    Check the 100% rule and eliminate overlaps

    Review

    Ensure that management, data, permissions, internal results and grant obligations are included. Confirm that a shared deliverable has not been counted twice.

  5. 05

    Assign codes and create a WBS dictionary

    Document

    Use stable identifiers such as 1.3.2 and record each package's scope, owner, output, acceptance criteria, boundaries and dependencies.

  6. 06

    Estimate resources, costs, risks and timing

    Plan

    Estimate the tasks needed under each package, staff availability, facilities, materials and costs; then develop the schedule and milestones.

  7. 07

    Approve the baseline and agree on reviews

    Govern

    Have the appropriate stakeholders approve the breakdown, retain a versioned baseline and establish how material changes will be requested, assessed and documented.

This sequence is illustrative. A small project may work through several steps in one meeting; a multinational consortium may require successive reviews and partner approvals.

06 / WORKED EXAMPLE

Complete research WBS example: developing sustainable packaging biomaterials

Imagine a fictional project to develop and validate a renewable-source biomaterial for packaging applications. A technology centre collaborates with a university research group and has 24 months to identify candidate formulations, characterise them, validate a prototype and document the findings. The example illustrates scope planning only; it does not describe a real funded project.

The overall project is coded 1.0 and divided into five major components. Each is broken down into second-level outputs. In this illustration, the lowest listed elements are managed as WBS work packages, although a real project might require further decomposition.

Numbered research WBS example with five components and ten work packages
CodeWBS elementPlanned evidence of completion
1.0Project: packaging biomaterialEntire project scope
1.1Management, methodology and complianceMajor component
1.1.1Research and coordination planApproved plan and responsibilities register
1.1.2Data management and compliance planValidated plan and applicable documentation
1.2Experimental formulationsMajor component
1.2.1Candidate formulation catalogueTraceable formulation and batch records
1.2.2Reproducible preparation protocolControlled version of the procedure
1.3Property characterisationMajor component
1.3.1Mechanical-property datasetData, testing conditions and quality controls
1.3.2Stability and barrier-property datasetTraceable measurements, methods and limitations
1.4Prototype and validationMajor component
1.4.1Documented pilot prototypeBatch information, characteristics and traceability
1.4.2Comparative validation reportReport assessed against agreed criteria
1.5Results and project closureMajor component
1.5.1Reusable results repositoryData and documentation deposited as specified in the plan
1.5.2Final scientific report and dissemination materialReviewed report and agreed communications

How to read the WBS hierarchy

Hierarchical breakdown of one project component

1.0 Project → 1.3 Characterisation → 1.3.1 Mechanical-property data and 1.3.2 Stability-property data. Laboratory tasks, team members and dates are subsequently planned around these packages.

Codes make references unambiguous in reports, meetings and documentation: the team can say that “1.3.2 is waiting for samples from 1.2.1” without confusing the expected output with an individual activity. The details of dependencies are recorded outside the scope tree, for instance in the schedule or a dependency register.

Dependencies and decisions revealed by the breakdown

Package 1.3.1 requires samples produced under 1.2.1 and a procedure agreed under 1.2.2. Prototype 1.4.1 will probably depend on sufficiently complete outputs from 1.3.1 and 1.3.2. However, these dependencies remain a planning assumption: the sequence must be confirmed against the actual methodology and resources.

If a formulation fails to meet target properties, the characterisation report can still be a valuable output. The team may test an alternative, revise the design or record the limitation. A package should not be considered complete simply because its allocated time has elapsed; nor should it be deemed a failure solely because a hoped-for positive finding did not emerge.

07 / WORK PACKAGE TEMPLATE

WBS dictionary: how to document a research work package

The tree shows the structure, but it does not explain what “finished” means. For that reason, a WBS is commonly accompanied by a WBS dictionary: a record for each manageable element covering scope, owner, requirements, exclusions, estimates, risks and acceptance criteria. This becomes particularly useful when several laboratories, external researchers or changes in team membership are involved.

Example WBS dictionary entry for package 1.3.2: stability and barrier data
FieldIllustrative entry
ID and title1.3.2 · Stability and barrier-property dataset
PurposeGenerate comparable experimental evidence for candidate formulations
OwnerLead characterisation researcher
Included scopeAgreed methods, testing, controls, data and issue logging
ExclusionsIndustrial scale-up and commercial certification, outside project scope
Inputs / dependenciesTraceable samples from 1.2.1 and protocol from 1.2.2
DeliverableDocumented dataset and short methods-and-results report
AcceptanceComplete metadata, documented controls, sample traceability and recorded technical review
RisksEquipment availability, repeatability and instrument failure
EstimatesStaff hours, materials, facilities and time window approved separately

The dictionary does not have to be lengthy. A small group may manage with a few fields, whereas a consortium subject to audits or contractual requirements may benefit from more detailed specifications. Acceptance criteria should verify the technical integrity of the work rather than dictate predetermined scientific conclusions.

What counts as evidence that a package is complete?

Depending on the package, evidence might include a version-controlled protocol, sample register, documented dataset, tested prototype, reviewed report or formal decision to proceed. Some outputs require internal sign-off or external submission. Where a funder's acceptance is required, that is a separate process governed by the relevant grant agreement.

08 / EUROPEAN PROJECTS

Work packages in Horizon Europe: how do they relate to a WBS?

European R&D grant proposals commonly organise the work plan into work packages (WPs) with objectives, tasks, responsible partners, resources, deliverables and milestones. The European Commission explains that grant agreements set specific reporting, monitoring and, where applicable, deliverable obligations.

A work package in an EU proposal is not necessarily identical to the lowest-level work package in a traditional WBS. In a European application, a WP may encompass several tasks and deliverables, serving as a relatively large project component. In PMI-style WBS terminology, a work package normally refers to the lowest level of the decomposition at which work is managed. One practical relationship might therefore be “EU WP → several internal WBS work packages → activities”, without assuming that different frameworks use identical terms.

Illustrative correspondence between WBS concepts and EU project work plans
EU proposal elementPurposePossible internal WBS representation
WP1 · ManagementCoordination, quality assurance, administrationComponent 1.1 and its subpackages
WP2 · DevelopmentExperimental workComponent 1.2 and part of 1.3
WP3 · ValidationPrototypes and evaluationComponent 1.4
WP4 · ResultsCommunication and exploitation as agreedComponent 1.5 and any required activities
Deliverable (D)Formally specified output for monitoring or submissionDeliverable identified within a component
Milestone (MS)Decision or control pointMilestone associated with one or more packages

This is an illustration: Horizon Europe does not necessarily require exactly four WPs or the names shown above. Forms, limits and obligations vary by programme, call, action type and topic. Always consult the current call documents and the specific grant agreement.

Example EU work package with tasks, a deliverable and a milestone

Fictional summary of a validation work package
FieldExample content
WP3Experimental validation of the biomaterial
ObjectiveCharacterise performance and limitations of candidate formulations
T3.1Conduct and quality-check mechanical tests
T3.2Conduct stability and barrier-property tests
D3.1Test report and documented dataset
MS3Technical review completed to determine readiness for prototyping
LeadPartner responsible for the WP under the consortium agreement

A WP description is a planning and contractual management instrument, not evidence that the proposed outputs have already been achieved. If funding is awarded, the approved obligations and formal amendment procedures take precedence.

09 / RESOURCES AND COSTS

How to connect your WBS to budgets and team capacity

Once the scope of each component has been identified, researchers can estimate staff time, critical equipment, materials and other associated costs. A WBS provides a structure for those estimates, but does not replace the official budget, eligibility rules or financial records attached to a grant.

Suppose the fictional project has €120,000 allocated to the scope under consideration, with the following initial component-level estimates. These figures are not recommended budgets for real projects and do not represent official costs under any European funding programme.

Fictional allocation of a €120,000 project budget
WBS componentEstimated costShare
1.1 Management and compliance€18,00015.0%
1.2 Formulations€31,00025.8%
1.3 Characterisation€29,00024.2%
1.4 Prototype and validation€30,00025.0%
1.5 Results and closure€12,00010.0%
Total€120,000100%

The split may help the team discuss feasibility. Before approval, however, it must be checked against personnel rates, overlapping workloads, equipment needs, purchasing, restricted funding and appropriate allowances. A cost percentage should never automatically be interpreted as the percentage of scientific progress achieved.

Avoid double-counting researchers and shared resources

When the same researcher works on both formulations and characterisation, their time should be allocated consistently with actual commitment. Equipment shared by two packages also needs an availability plan. Activities may be linked to multiple outputs, but a cost should not be counted twice merely because it appears in two reports.

A project portfolio management (PPM) approach is particularly relevant when the same constraints affect several projects rather than a single one.

10 / MONITORING

How to monitor work packages without misrepresenting scientific progress

A WBS defines what needs to be produced; monitoring requires additional information about what has been completed, what is under review and what depends on a third party. Marking a task as complete does not necessarily mean its associated deliverable has been accepted. Similarly, it is misleading to claim that research is 70% complete simply because 70% of its planned duration has passed.

Measure progress against evidence and agreed criteria

For a package such as a “characterisation dataset”, useful statuses might be: protocol ready, data collected, controls completed, technical review passed and output archived. Only use a numerical percentage when there is a defensible weighting method. If progress cannot be reliably quantified, a qualitative status with an explanation and review date is preferable to an apparently precise number.

Illustrative monitoring of three WBS elements
ElementStatusEvidence / next decision
1.2.2 · Preparation protocolInternally validatedVersion-controlled procedure; testing can begin
1.3.2 · Stability dataUnder reviewReview controls and document issues
1.4.1 · Pilot prototypeNot startedAwaiting characterisation review

Monitoring may include indicators such as packages whose acceptance criteria have been satisfied, deliverables awaiting approval, schedule risks and resource demand. For wider research performance measurement, see our seven research output indicators and research group KPIs. Such indicators should never replace responsible scientific assessment.

11 / RESEARCH INTEGRATION

Connecting the WBS with research lines, theses, papers and documents

An academic project does not exist in isolation. Its outputs may contribute to a doctorate, generate papers, depend on shared data or form part of a longer-term research line. To prevent disconnected records, it helps to establish clear links between WBS components and these research activities, without assuming every output belongs exclusively to one package.

  • Research lines: show the scientific direction or strategic field to which a project contributes; they do not replace its WBS.
  • Doctoral theses: may draw on data, protocols or findings from several packages, while retaining their own supervision, planning and assessment requirements.
  • Publications: connect to scientific findings, but editorial review may continue long after the experimental work has finished.
  • Documents and datasets: provide evidence of work completed or scientific outputs and require suitable version control and access rules.
  • Meetings, tasks and deadlines: capture operational decisions, helping each package progress while retaining an audit trail of issues.
  • Funding calls: once a grant is awarded, the agreed scope, budget and deliverables may constrain the WBS and subsequent changes.

These links are particularly useful for teams with several PIs, external collaborators or doctoral researchers. They also simplify reporting by making it possible to find the documentation associated with an output without reconstructing a long history of email threads.

Which software should you use to organise a research WBS?

For a straightforward project, a spreadsheet or a numbered outline may be sufficient. As dependencies and revisions multiply, tools that connect projects, tasks, milestones, owners, permissions and documentation can be helpful. Not every project management system offers a dedicated WBS tree editor, automatic control-account calculations or resource scenario modelling; these functions must be verified for each product.

KaiperKit helps organise research projects and link them to research lines, scientific publications, doctoral theses, funding calls, tasks and documents. These functions can support monitoring of a breakdown agreed by the team, but they should not be presented as a dedicated WBS module with automatic hierarchical numbering without checking that such a feature is actually available.

12 / REUSABLE TEMPLATE

Basic WBS template for a research project

This generic structure is a starting point for an initial planning meeting. Adapt it to the research question, funding commitments, available data and the organisation of the team. Not every research project needs every category, nor must every team arrange its scope in precisely this way.

Illustrative template for reviewing the scope of a research project
Suggested codeOutput or componentReview question
1.0Scientific projectHas the agreed overall scope been defined?
1.1Scientific design and requirementsWhich protocols, approvals and decisions must be documented?
1.2Data, samples and input resourcesWhich inputs and supporting evidence are required?
1.3Documented experiments or developmentsWhich verifiable outputs will be produced?
1.4Analysis and validationHow will the quality of the work be assessed?
1.5Communication, knowledge transfer and closureWhich outputs should be preserved or shared?
1.6Coordination and cross-cutting obligationsWhat management, ethics, data and reporting work remains?

Add lower-level elements as needed and create a concise dictionary entry for each final work package. A WBS can also be organised by subsystems, scientific domains or products, provided the hierarchy remains understandable and covers the full scope without overlaps.

Checklist before approving a research WBS

  • Does every element have an unambiguous name and scope?
  • Are all required internal and external outputs represented?
  • Is a clear operational owner assigned to each work package?
  • Can completion be verified through documented evidence?
  • Have relevant management, ethics, data protection and reporting duties been considered?
  • Are duplicate elements avoided across different branches?
  • Is the level of detail sufficient without becoming excessive?
  • Have critical dependencies and resource requirements been identified?
  • Are approval and change-control arrangements understood?
  • Can rigorous negative results still be documented and accepted where appropriate?
13 / COMMON MISTAKES

Common mistakes when defining research work packages

  • Confusing scope with the schedule: structuring the WBS solely by months hides which outputs have actually been committed.
  • Listing activities without defining outputs: “carry out tests” does not establish what evidence will demonstrate completion.
  • Overlooking management and compliance: approvals, coordination, data management, reporting and reviews also require work.
  • Promising uncertain scientific results: journal acceptance and a positive hypothesis test cannot be guaranteed by placing them in a WBS.
  • Creating hundreds of tiny elements: excessive decomposition adds bureaucracy and makes the project harder to oversee.
  • Double-counting people or outputs: a dataset reused in several papers should not appear as if it were two separate original datasets.
  • Changing the scope without a record: undocumented changes affect commitments, costs and dates without a clear rationale.
  • Copying an EU proposal template without adapting it: WP and reporting requirements differ by call and grant agreement.
  • Equating task completion with scientific quality: finishing activities does not prove that the findings are valid; technical and methodological review is still needed.

The remedy is not an even longer document. It is a structure precise enough to guide decisions and flexible enough to incorporate experimental learning through controlled changes.

14 / FREQUENTLY ASKED QUESTIONS

FAQs about research WBS and R&D work packages

What does WBS mean in a research project?

WBS stands for Work Breakdown Structure. It is a hierarchical decomposition of the outputs and components that make up the agreed scope of a research project.

Is there a difference between WBS and the Spanish abbreviation EDT?

No. EDT, short for Estructura de Desglose del Trabajo, is the standard Spanish equivalent of WBS. The way the structure is displayed may vary between organisations.

What is a work package within a WBS?

In PMI-style terminology, a work package is the lowest level of the breakdown at which scope, effort, cost, duration and resources can be estimated and managed. An EU grant proposal's WP may cover several tasks and deliverables and may therefore be broader than that lowest-level element.

How many levels should an R&D WBS contain?

There is no fixed number. Decompose the project until its components can be understood, estimated, assigned and reviewed without creating unnecessary administrative work.

Does a WBS replace a Gantt chart?

No. A WBS organises the scope; a Gantt chart displays activities, dates, sequencing and dependencies. They are complementary planning tools.

What is the 100% rule in a WBS?

The structure should cover the entire approved scope and exclude unrelated work. Child elements should account for the whole parent element without duplicating outputs. It does not mean allocating arbitrary, equal progress percentages to tasks.

What happens if the research produces negative findings?

If agreed methods and acceptance conditions have been met, valid data, a findings report or rigorously documented negative conclusions may constitute legitimate deliverables. Material changes to the scope or funder commitments must follow the relevant approval process.

Is a document explicitly called a WBS mandatory in Horizon Europe?

Not necessarily. Many EU proposals require a work plan structured around work packages, tasks, deliverables and milestones, but exact documentation varies by call and application form. An internal WBS may help develop that plan.

Do I need specialist software to create a research WBS?

Not always. A small project may be managed using a well-maintained table or hierarchical outline. More complex projects can benefit from connecting the breakdown with owners, tasks, documentation, deadlines and scope reviews.

15 / CONCLUSIONS

A well-designed WBS turns research scope into coordinated work

The value of a WBS for a scientific research project does not lie in creating an elaborate diagram. It lies in identifying the outputs and components that make up the project, who can take responsibility for them and what evidence will verify completion. This breakdown gives teams a clearer basis for planning activities, resources, budgets and decisions.

Scientific work calls for one crucial adaptation: distinguish manageable deliverables from uncertain findings, allow justified revisions and preserve the value of rigorous negative results. R&D work packages are helpful when they improve scientific coordination, not when they reduce research to ticking boxes.

RESEARCH PROJECT MANAGEMENTConnect projects, tasks, milestones and documents in one workspace.
Explore KaiperKit project management

Sources and further reading

The WBS examples, budgets, roles, schedules and acceptance criteria used in this guide are fictional and intended to explain the methodology. For formal definitions and project-planning guidance, consult: